How to count non-overlapping months of PMP experience
PMI counts calendar months, not projects, and counts each month once. Worked examples of overlapping projects, gaps, and the 10-year window.
PMI measures experience in months. It does not matter how many projects you led or how many hours you worked. What matters is the number of distinct calendar months, inside the last 10 years, in which you were leading at least one project.
That sounds simple, and it trips up a surprising number of applicants.
The rule
Every project is recorded separately on the application, with its own start and end date. PMI then counts the months those projects cover, and a month covered by more than one project is counted once.
PMI's own example:
- Project I ran from 1 January to 31 March. That is three months.
- Project II ran from 1 February to 31 May. On its own that is four months.
- February and March are covered by both projects, so they are counted once.
- Together the two projects give five months: January through May.
Adding the two durations gives seven. The correct answer is five.
A longer worked example
Suppose you have a bachelor's degree, so you need 36 months, and these are your projects:
| Project | Start | End | Months on its own |
|---|---|---|---|
| A. Warehouse system rollout | March 2021 | February 2022 | 12 |
| B. Site relocation | November 2021 | June 2022 | 8 |
| C. Training program build | September 2022 | August 2023 | 12 |
| D. Vendor transition | June 2023 | January 2024 | 8 |
Added up, that is 40 months, which looks like enough.
Now count calendar months:
- A and B together run from March 2021 to June 2022 without a break. That is 16 months, not 20, because November 2021 through February 2022 is shared.
- July and August 2022 have no project. They count for nothing.
- C and D together run from September 2022 to January 2024. That is 17 months, not 20, because June through August 2023 is shared.
The real total is 16 + 17 = 33 months. This applicant is three months short and needs another project, or a later application date once more experience has built up.
The experience calculator on this site does this count for you.
The 10-year window
Only months within the 10 years before you submit the application count.
If you submit in the middle of November 2026, the window reaches back to the middle of November 2016. A project that ran from June 2016 to May 2017 contributes only its last six months or so.
Two practical consequences:
- Older projects lose months as you wait. If you depend on a project from nine or ten years ago, every month you delay costs you a month of eligible experience.
- Recent projects are safer. If you have a choice, build your total from the most recent work.
Which dates to use
Use the dates of your involvement in leading the project.
- The start date is when you began leading work on it, which may be later than when the project was conceived.
- The end date is when your leadership role ended, which may be earlier than the project's final close if you handed it over.
If you joined a three-year program for its final year, you have twelve months, not thirty-six.
If you list a project that is still in progress, count only the months completed up to the date you submit.
Common mistakes
Adding durations. This is the mistake in the worked example above. Always count calendar months on a timeline.
Counting gaps. Time between projects is not project experience, even if you were employed as a project manager throughout.
Rounding up. A project that ran from the 20th of one month to the 5th of the next did not take two months of your leadership. Be conservative with partial months at the edges. If an audit compares your dates with what a verifier remembers, generous rounding is what stands out.
Listing everything. You do not get extra credit for exceeding the requirement by years. Choose the projects that are easiest to describe and verify, clear the requirement with a margin of a few months, and stop.
Forgetting the window. A project counted in full that began eleven years ago is the easiest error for a reviewer to spot.
A quick method
- Draw a line of months covering the last 10 years.
- For each project, shade the months from your start to your end.
- Count the shaded months. A month shaded twice still counts once.
- Compare the count with your requirement: 60, 48, 36, or 24 months depending on your education.
If the count is short by a small number, look again at your list for real projects you overlooked. Short assignments such as a system migration, an office move, or a one-time audit preparation are often left off because they did not feel like "project management" at the time. The guide on what counts as project experience can help you spot them.